We offer a one-stop service for shipping large items by land from Thailand, including customs clearance and tax payment.

 Customer Case    |      2025-01-15

Dongguan 230 tons government project cargo transportation to Thailand Loei case

The business of listed company in Dongguan and the construction project of the Thai border has been successfully negotiated. Within 10 days, it is necessary to ship 23 tons of airport gates and security inspection equipment to Thailand. Due to the time, the full-route land transportation arrangement is arranged for this transportation.

 

The transportation is as follows:

The first batch of goods will be shipped on November 5th. The detailed plan is as follows:

Dongguan Chaosh---Thailand Loei plan and operation details are numbered as follows:

1, Dongguan Chaoshan--Pingxiang bonded area: 3-meter high barrier----1-1.5 days

2, Pingxiang bonded area for local loading and warehousing----1 day3, Spring River cargo yard, need to unload and change to Vietnam's car---1 day

4, Vietnam change car after - Laos Vientiane2 days

5, Laos Sand Bay bonded area/truck, change to Thai truck—0.5 days

6, Thailand transits Mu Dan Han

7, after transiting to Loei unloading place—0.5 days

Total time: 5 days-7 days

 

This cargo is high, with a height of 2.7 meters. Therefore, the vehicle scheme is a high barrier truck.

The first batch of transportation was completed according to plan, and the customer was asked to prepare the customs declaration materials in advance. Our company arranged for the customs declaration officer to do the customs declaration, gave the customer draft for proofreading, and sent the data of the customs declaration form made by the customer to the Thai customs clearance colleague according to the reference commodity code for export. pre-checked the details of Thai customs clearance and the required documents, etc., as well as the handling of FE, which can enjoy the tariff preferences of the ASEAN countries, etc., and all the docking work was completed before the goods were loaded.

The transportation process was very smooth, and the customs was also very smooth. During the journey, our company had a special dispatch to arrange for follow-up and feedback on the cargo yards. This cargo is worth 0 million US dollars, and our company has also arranged for the insurance company to purchase insurance. When the goods arrived at the destination, the customer also arranged for intermediateary personnel to check the goods, etc., and only after no error was made the signing.

 

For large projects with high value, our company has done lot of details. The previous work is the guide for the transportation process. Judgment and advance preparation of some details that may be encountered during the transportation process can make order delivery perfect.